2025-01-23

9th,Jan,2025 The Helian industrical park 14.3MWp PV solar plants has totally parallel in grid successfully .This rooftop pv solar plants was developed and constructed by CM technology, which is ERGO solar’s parent company.This big projects is consist by Phase I 7188.56KWp and Phase II 7135.05KWp
24279pcs Jinko 72HL4-BDV 590W solar panels and 32sets 300KW Huawei + 12sets 196KW Huawei inverters was installed on this industrical park. The whole project went through a construction period of 5 months. The average annual power generation of this project is about 15.74 million kWh, and 100% of the project’s power generation is sold to State Grid Corporation of China. It can reduce 3650 tons of coal per month for usage, and carbon dioxide emissions by 10000 tons per year.
At the project site, CM Technology invited senior management from partners such as Haiju New Energy, Helian Industrial Park, and the Director of the Investment Promotion Bureau of Haimen Economic Development Zone to attend the celebration ceremony of the project